La Broquerie ponders new library, joining $190-million wastewater plant
Advertisement
Hey there, time traveller!
This article was published 29/03/2024 (968 days ago), so information in it may no longer be current.
The biggest capital project in La Broquerie this year is the $1.28-million ice plant replacement at the HyLife Centre, approved in February by council.
But a $5-million loan is in the proposed $10.41-million 2024 RM budget on the longshot chance council decides to join the $190-million Red-Seine-Rat wastewater plant after a study is completed this year.
“That $5 million was put there, and you’ll probably see that there for the next couple years until we move forward on a project for the lagoon,” said Reeve Ivan Normandeau in explaining the improbability that any decision would be made this year.
Normandeau added that they were being proactive as the lagoon approaches capacity.
“The reason we did this (study) is basically if we would tap into the regional wastewater, we wouldn’t have to build any lagoons going forward for future years to come,” he added.
The wastewater plant will be situated north of Niverville and service the RMs of Hanover, Richot, and Tache and the Town of Niverville. The communities of Mitchell, Blumenort, New Bothwell, Landmark, Lorette, Ste. Agathe, St. Adolphe and Ile des Chenes will be serviced by the plant. De Salaberry and Steinbach have also expressed interest in the plant.
The plan is to be operational by 2027 or 2028. The last La Broquerie lagoon expansion in 2015 was budgeted at $6 million.
A $25,000 feasibility study for the municipal library was also in this year’s proposed budget. The library is currently in École Saint-Joachim, the DSFM French-language school in town. During the school year, it is reserved for students and staff only until after kids go home at 3:30 p.m.
“The division has told us that they’re eventually going to get away from having the libraries in the schools itself, so we’re looking to see if it’s worth building a new one offsite,” said Normandeau.
“The library itself had the funds in place to do this (study), so they’re looking to do a feasibility study on where it should be going and what else should be part of it.”
The next largest capital expenditure is $337,500 for the St Joseph West Trail. Bids were being sought for a mile of asphalt-topped path on the north side of St. Joseph Road from Carriere Road (40E) to St. Denis Road (41E), one mile south of Highway 52 near a built up rural residential area.
The budget lists the money coming from the general fund ($153,450) and reserves ($184,050). Normandeau has said La Broquerie is receiving $125,000 per year in grants for trails.
He added that a resident survey conducted about 10 years ago found active living to be a top priority.
“We did a survey years ago about what people like about the RM of La Broquerie and one of the biggest things coming back is the walking trails, not only in the town but also in the subdivisions and in the rural area. It’s getting used a lot by a lot of demographics,” said Normandeau.
“Especially in the new developments, it’s something that we find is important for the residents to be safe to walk in the rural area, and also to have a walking trail for the kids.”
Other capital items included a Loewen Boulevard upgrade ($277,600), tractor ($270,000), Eastgate Drive improvements ($150,000), grader repairs ($75,000), and mowers ($25,000).
There was no borrowing expected to be needed this year. Expected end dates for past loans include the 2006 municipal office and lagoon expansion (2026), 2013 Normandeau Bay reconstruction (2028), 2015 Hylife Centre expansion (2029), 2016 lagoon expansion (2031), 2018 tertiary project (2038), and 2022 firehall construction (2042).
The RM is paying $579,421 for buildings and paving debenture debt charges, and $374,681 in utility debentures for three lagoon loans.
Taxes in La Broquerie are to go up nine percent for rural residents and 5.5 percent for those in the LUD if council passed the proposed rates March 27. The total mill rates would be 16.973 for rural, and 16.493 for the LUD.
That is an increase of $184 to $2,149 for the average rural home assessed at $281,311, and an increase of $122 to $2,221 for the average LUD home assessed at $315,733.
“Unfortunately it’s a small tax increase, but overall we’ve increased our gravel to maintain our gravel roads because we had such a rough spring last year; and also our drainage and dust-proofing,” said Normandeau.
Transportation service expenses are the biggest part of the budget and were proposed to go up from $2.07 million spent last year to $2.35 million this year, a $280,000 increase. There is $600,000 proposed to be spent on gravel alone, up from last year’s budget of $475,000 ($523,744 was actually spent in 2023).
“That’s the main one, and then we’re keeping up with our equipment purchases,” said Normandeau.
The second-largest expense is general government services at $1.28 million, with administrative and office staff making up $734,466 of that. Protective services including bylaw enforcement, fire protection and more are at $606,279, up over $35,000 from what was spent last year.
Recreation and cultural services get $1 million this year, up $40,000. That includes $51,646 for the municipal library.
Every municipality must submit a five-year capital plan to the Province. La Broquerie’s includes a $15-million community resource centre in 2026.
Normandeau stressed the five-year plan is a wishlist, and not something close to becoming reality yet. He added that there is not any specific idea being leaned towards, saying it could be anything and gave the examples of a fieldhouse or library.
“It can change 20 times before it comes to fruition,” said Normandeau.
With files from Svjetlana Mlinarevic and Ian Froese.